Hillfoot commenced works on the project by installing a piling mat, followed by reduced-level excavation, pile cropping, and internal drainage works. The team worked closely alongside the steel fixers throughout this phase. At a later stage, Hillfoot returned to complete the installation of the main drainage network and attenuation tank.